The Technical Upgrade (phase one) is moving along as planned. We are making plans to move to the last testing environment at the end of this month as we are just two months away from go-live for this phase.

Communications and change management plans are also forming. The Functional Upgrade (phase two) has been scoped to 17 initiatives. Close to half of these groups have kicked off and are actively chartering and gathering requirements. The other half will be kicking off in the upcoming weeks. You can now get weekly, high-level updates regarding each initiative in the project status dashboard sent by Carrie Otto.